Construction Progress
Thursday, June 25, 2009
 |
 |
6/25/2009
Excavation in front of the hospital. |
6/25/2009
Construction behind the hospital. |
Mission 2012 Update
Wednesday, June 3, 2009
We are now six weeks into our project and you can see some
significant changes already taking place on the Lourdes campus.
- Excavation at the front of the hospital is well underway.
Work has begun to place forms for the footers of the new section of
building that will eventually become part of the Emergency
Department.
- The construction behind the hospital is moving forward and
shortly you will begin to see the shell of that section of building
come together. This will house two new OR suites and the open
MRI.
- The new entrance into Lot C located at the bottom of Lourdes
Road will be paved and open to traffic in the next two to three
weeks.
- Construction for the flood wall is tentatively scheduled to
begin in early July. Phase I of this part of the project will
begin on the east end of the campus, off Lourdes Road.
 |
 |
6/3/2009
Excavation in front of the hospital. |
5/21/2009
Construction behind the hospital. |
We'd like to remind everyone to please pay attention to the
parking designations. Parking and using the entrance most
convenient to your destination will ensure that you find your way
easily.