Flood Wall Progress
Wednesday, December 30, 2009
Flood wall construction in front of the Ozanam and DePaul
entrances is nearing completion. The fencing around this area is
expected to be removed by Monday, January 4th. Flood gates for this
portion of the flood wall will be installed at a later date.
The flood gates behind the Lourdes Tower (on the Lourdes Road
side of the hospital) are scheduled to be installed the week of
January 11th. The installation should take about 15 days. Once the
installation begins, a temporary change in the current traffic
pattern will be in effect.
Emergency Department, Surgical Suites, and Open MRI
Wednesday, December 30, 2009
Construction Progress
Tuesday, December 22, 2009
Emergency Department (ED)
Interior work on the ED project continues to progress quickly.
Much of the drywall, electrical, and heating, ventilating, and air
conditioning (HVAC) work is complete or currently in progress. This
phase of the ED construction is expected to be complete by May
2010. The second phase of work is expected to begin in May or June
2010.
Surgical Suites/Open MRI
Construction of the new Surgical Suites and Open MRI is also
moving along nicely. Drywall is still being installed in some
areas, and HVAC and electric work are nearly complete.
Flood Wall
Four of the flood gates arrived last week. These flood gates
will be installed on the Lourdes Road side of the hospital and
behind the hospital power plant. Installation, mostly staging and
preparation, of the gates is slated to begin the week of
December 21st. It will take about 14 days to install each gate.
Please be aware of changes in traffic flow and additional
workers/equipment in the area.
Construction of the flood wall
has been
progressing
well. At this point in time,
the hospital is about 65% protected in the event of a
flood. By
early
January, the hospital should be completely protected by the flood
wall on the Lourdes
Roadside of the
hospital
past
the power plant. Flood wall construction
will resume in March and it is
anticipated that the flood wall will be complete by the end of
April.